| Type of Development | = | Peaking Run-of-River (PRoR) |
| Location | = | Bagmati Province, Dolakha District, Bigu Rural Municipality Ward No. 1, |
| Headworks Location | = | Bigu Rural Municipality Ward No. 1, Lamabagar |
| Powerhouse Location | = | Bigu Rural Municipality Ward No. 1, Gongar Gaon |
| Maximum Output | = | 456 MW |
| Annual Energy | = | 2,281 GWh |
| Gross Head | = | 822 m |
| Design Discharge | = | 66.0 m 3 /sec |
| Hydrology | ||
| Catchment Area | = | 1,745 km 2 |
| Min. Mean Monthly Flow | = | 14.1 m 3/sec. |
| Mean Annual Flow | = | 67.2 m3/sec. |
| Design flood Q1,000 | = | 885.0 m3/sec |
| Diversion Dam | = | 22 m x 60.0 m (H x L) |
| Live Storage | = | 1.2 Million m3 |
| Settling Basins | = | 2 Nos. L=225 m |
| Headrace Tunnel | = | 8.4 km (Cross Sectional Area = 32.14 m2) |
| Penstock (Vertical Shaft and Horizontal Tunnel) | = | 1,134.0 m |
| Power House (Underground) | = | 142.0m x 13.0m x 25.0 m (L x B x H) |
| Number of units | = | 6 |
| Tailrace Tunnel | = | 2.9 km (Cross Sectional Area = 35.0 m2) |
| Access Road from Charikot of Dolakha District | = | 68.0 km |
| Transmission line | = | 220 kV Double Circuit, 47.0 km (Gongar to Khimti Substation) |
| Construction Cost | = | NRs.35.29 Billion equivalent to US$ 441 Million (Excluding Interest During Construction) |
| Construction Time Period | = | 6 Years |